Sewer replacement Erlhofer Straße, Stelzenhofstraße and Epprechtsteinstraße
UPDATE: 30.11.2023 - Traffic opening at the beginning to middle of week 51, construction expected to resume in March 2024.
_____________________
The municipal measure to replace the sewers in Erlhofer Straße, Stelzenhofstraße and Epprechtsteinstraße begins on 09.10.2023.
In 2023, the section will begin in Erlhofer Straße at the level of the former petrol station, branch off into Stelzenhofstraße and end at the level of Epprechtsteinstraße.
In spring 2024, the project will continue on Epprechtsteinstraße as far as Luisenburgstraße. Due to the time of year, however, there may be delays due to the weather. With the interruption of the work at the end of 2023, the traffic areas will be reopened to traffic until the start of construction in 2024. During the work, the affected sections will be closed to through traffic. However, the footpaths will remain usable. Residents will be able to access their properties. However, temporary obstructions must be expected in the area of the current construction site.
City bus routes 1 and 8 will be diverted via Erlhofer Straße, Kösseinestraße and Fichtelgebirgsstraße (see separate press release from Hof-Bus GmbH).
The bus stop at the VFB Moschendorf sports home will not be served during the construction period in 2023.
The city of Hof asks for your understanding, also on behalf of the construction company AS-Bau GmbH.
Start of construction 09.10.2023 Expected end of construction 3rd quarter 2024
Contact personJörg Raml Phone: 09281 / 815 - 1570 E-mail:joerg.raml@stadt-hof.de | Executing company
AS Bau Hof GmbH Stelzenhofstraße 28 95032 Hof |