Sewer replacement Oberkotzauer Str.
From Ostpreußenstraße to Oberkotzauer Straße, house number 34
On behalf of the city of Hof, Luding GmbH will begin sewer renovation work on Oberkotzauer Straße on 1 September 2025. The construction project will extend from Ostpreußenstraße to Oberkotzauer Straße, house number 34.
Completion is scheduled for 12 December 2025.
The work is planned to be carried out under full closure, with the closed construction area limited to a maximum of two sections.
Residents will be able to access their properties. However, temporary disruptions are to be expected in the area of the current construction site.
The city of Hof apologises for any inconvenience on behalf of the construction company Luding GmbH.
Start of construction: 01/09/2025
Planned completion of construction: 12.12.2025
Contact personJonah Friedrich Phone: | Executing company
Luding GmbH 95194 Regnitzlosau |