City of Hof launches road renovation programme for 2025

14 roads will receive a new asphalt surface course in the coming weeks.

In July, the city of Hof begins repairing the roads. A total of 14 roads will receive a new asphalt surface layer in the coming weeks. The work will be carried out in sections and will lead to short-term full road closures.

 

These roads are part of the programme

  • Am Otterberg from Hügelstraße to Am Otterberg No.91: Monday 14.07.2025 to Thursday 17.07.2025
  • Krötenhofer Weg from Südring to Hermann-Löns-Straße: Thursday 17.07.2025 to Monday 28.07.2025
  • Richard-Wagner-Straße from Eppenreuther-Straße to the Münsterweg junction: Monday 28.07.2025 to Thursday 31.07.2025
  • Döberlitzer Straße from Ostendstraße to Döberlitzer Str. 54: Friday 08.08.2025 to Thursday 14.08.2025
  • Pinzigweg from Rosa-Opitz-Platz to Breslaustraße: Thursday 14/08/2025 to Monday 25/08/2025
  • Sophienberg from Sophienstraße to Königsstraße: Monday 25/08/2025 to Tuesday 02/09/2025
  • Sophienstrasse from Sophienberg to Theresienstrasse: Tuesday 02/09/2025 to Friday 05/09/2025
  • Wilhelmstraße from Luitpoldstraße to Kreuzsteinstraße: Friday 05/09/2025 to Wednesday 10/09/2025
  • Wirthstraße, Gabelsberger Straße intersection: Friday 05/09/2025 to Wednesday 10/09/2025
  • Von-der-Tann-Straße from Marienstraße to Wilhelmstraße: Monday 22/09/2025 to Thursday 25/09/2025
  • Landwehrstraße from Sedanstraße to Orleansstraße: Thursday 25/09/2025 to Tuesday 30/09/2025
  • Rupprechtstraße from August-Mohl-Straße to Yorckstraße: Monday 13.10.2025 to Thursday 16.10.2025
  • Am Geigengrund from the Alte Gärtnerei junction: Monday 13/10/2025 to Thursday 16/10/2025
  • Meiselfelder Straße from Kulmbacher Straße to just before the left-hand bend: Thursday 16/10/2025 to Tuesday 21/10/2025

 

How the work will proceed

The construction work is scheduled to take approx. one week per road:

  • Day 1-2: The old asphalt surface course will be milled off by approx. 2-4 cm, paving components such as manholes and valve caps will be renewed or adapted.
  • Day 3: A new asphalt surface course of approx. 4 cm thickness is laid.
  • Day 4: Reworking, joint sealing and, if necessary, new markings are carried out.

The affected road sections will be fully closed during the construction work. Residents will receive a personalised information letter with details of the work approximately two weeks before the work begins. The tarmacing work can only be carried out in dry weather conditions; short-term postponements cannot be ruled out.

 

Information for road users

The city of Hof asks all citizens and road users for their understanding for the restrictions during the construction period. The aim is to permanently improve the traffic areas and sustainably maintain the infrastructure. The detailed construction phases and the planned time periods can be viewed on the Hof city website.