Bridge Mittlerer Anger
Work to dismantle the Angerbrücke bridge will begin on 26 August 2025. The work will begin with site clearance, which includes cutting back the surrounding bushes, mowing the grass and other preparatory measures in the immediate vicinity of the bridge. The necessary traffic facilities have been set up as of today and access to the bridge is now closed.
Phase 1: Demolition of the Anger Bridge
Period: August 2025 - October 2025
In the second week of September, the actual construction site set-up will begin with construction containers, a site office, excavators and the first drilling equipment. Demolition work begins on the Mühldamm side first. A special process ensures that the work is carried out in an environmentally friendly manner: Pipes are laid into the Saale river, over which slabs are laid. This allows water and fish to pass unhindered, while the removed material falls onto the slabs and is then collected and transported away by excavators.
The first construction phase will take around five weeks. After that, work will shift to the side of the factory line and the other side of the bridge will be demolished in the same way. During the winter months, the construction site will take a break due to the weather.
Phase 2: New construction of the Anger Bridge
Period: September 2025 - November 2026
In this phase, the new structure will be built in individual sections. We would like to point out that there may be temporary noise disturbances during the work and ask all residents for their understanding.
Contact personStefan Breitenberger Phone: | Executing company
Structural and civil engineering Reichenbach
|